In 2024, City Council commissioned a sewer rate study to consider increasing sanitary sewer rates over the next 5 years. The city of Salinas owns and operates the municipal sanitary sewer system that serves residents and businesses across approximately 12,430 acres. This system includes over 280 miles of gravity sewer mains, force mains and 11 lift stations, which convey sewage to the Regional Wastewater Treatment Plant operated by Monterey One Water (M1W). The rate study will assess the potential implications of on going operating and maintenance costs, capital improvement program needs, current and future debt obligations, changing customer demands, and future development. Salinas’ wastewater program is a self-supporting enterprise of the City that includes the sanitary sewer system, staff, equipment, and supplies and debt obligations. The wastewater program is required to generate the revenues (through rate payer service fees) to cover the ongoing costs of operations, maintenance, administration, regulatory compliance, debt service, capital improvements and maintenance of prudent financial reserves. For FY 25-26 the equivalent dwelling unit (EDU) sewer rate is anticipated to be $16.35.

The tentative schedule for consideration of new sewer rates is:

March 4, 2025 | Finance Committee - Presentation of Rate Analysis Findings

March 11, 2025 | City Council #1 - Presentation of Rate Analysis Findings

April 8, 2025 | Finance Committee - Recommend approval of the Rate Study and Rate Schedule

April 22, 2025 | City Council #2 - Request approval of the Rate Study and Rate Schedule; Request authorization to Proceed with Proposition 218 Process; Set Public Hearing Date for June 17, 2025 and Protest Process (45-day Notice) 

June 17, 2025 | City Council – Staff informed the City Council of inaccuracies in the Rate Schedule.

July 1, 2025 | City Council – Directed staff to distribute Proposition 218 Public Hearing Notices for proposed sewer rate increases based on the updated Sewer Rate Study and Sewer Rate Schedule with public hearing date set for September 23, 2025.

August 25, 2025 | City Council - End or deadline of protest period for City to receive written objections from property owners under AB 2257

September 23, 2025 | City Council - Public Hearing and Sewer Rate Adoption

October 1, 2025 | New rates effective

 

Council Actions and Background Documents


January 10, 2012 

City Council accepted the sewer rate study and approved Proposition 218 to increase sewer rates to $5.45.


Meeting Documents:

Meeting Video: https://www.youtube.com/watch?v=3t6pSjowXfk


May 2, 2023

City Council adopted the Sanitary Sewer Master Plan Update.

 

Meeting Documents: 

Meeting Video: https://www.youtube.com/watch?v=3v5ZRof9RJ8


September 24, 2024 

City Council approved an update to the Sanitary Sewer Development Impact Fees.

 

Meeting Documents:

Meeting Video: https://www.youtube.com/watch?v=UaTQcXqK88Y


March 4, 2025

Finance Committee received the sewer rate study findings and recommended completion of the study using scenario one.



Meeting Documents:

Meeting Video: https://www.youtube.com/watch?v=d8hgz77O9RI


March 11, 2025

City Council received the sewer rate study findings and approved the completion of the study using scenario one.

 

Meeting Documents:

Meeting Video: https://www.youtube.com/watch?v=IY2ZEV2Iz88


April 8, 2025

Finance Committee recommended approval of the Sanitary Sewer Rate Study and Rate Schedule for presentation to City Council.


Meeting Documents:

Meeting Video: https://www.youtube.com/watch?v=2WOz1njpGzA


April 22, 2025 

Request approval of the Rate Study and Rate Schedule; Request authorization to Proceed with Proposition 218 Process; Set Public Hearing Date for June 17, 2025 and Protest Process (45-day Notice)

 

Meeting Docs:

Meeting Video: https://www.youtube.com/watch?v=KILFu38_PI0 


June 17, 2025

Staff informed the City Council of inaccuracies in the Rate Schedule.

 

Meeting Documents:

Meeting Video: https://www.youtube.com/watch?v=LR_QLG7JlHA


July 1, 2025

Directed staff to distribute Proposition 218 Public Hearing Notices for proposed sewer rate increases based on the updated Sewer Rate Study and Sewer Rate Schedule with public hearing date set for September 23, 2025.

 

Meeting Documents:

Meeting Video: https://www.youtube.com/watch?v=pbbu1ARkkRM

 

For additional information regarding the proposed sewer rate increase, please contact:

City of Salinas Public Works Department, Engineering Division

200 Lincoln Ave, City Hall, Second Floor, Salinas, CA 93905

pubworks@ci.salinas.ca.us or (831) 758-7381


Sewer Rate Study 2025

The City of Salinas has performed a 2025 Sanitary Sewer Rate Study for existing and potential future sewer utility user rates within the City based on future CIP needs and conclusions of the 2023 Sanitary Sewer Master Plan Update. City sewer rates and fees were last approved for adjustments in 2012 through proposition 218 protest vote process. This Spring 2025, the Public Works Department is bringing forth a new 2025 Sanitary Sewer Rate Study for Consideration.